Construction Work Update July 2023

State of progress on 6th July 2023:

  • the construction of the building and the roofing is complete and sheet metalwork is now being installed.

Current work ongoing inside the building:

  • plastering is ongoing - 70% complete,
  • installation of underfloor systems - 90% complete,
  • underfloor installations - 40% complete,
  • construction of cardboard plasterboard partition walls on the 3rd floor - 40% complete,
  • thermal insulation of the garage ceiling – 100% complete.

Outside the building:

  •  work on the elevation - 62% complete,
  •  installation of aluminium-glass facades and windows - 71% complete,
  •  the construction of foundations of fire roads and sidewalks has begun.

In July, work will begin on laying flooring, finishing and painting walls, and the installation of suspended ceilings.